Blackout in 13 States Leaves 70 Million Without Electricity - Folha de S.Paulo
As of 7:45 PM, the NOS (National Electrical System Operator) was still working to re-establish electrical energy to the Northeast. "We aren't happy with the time being taken for recomposition, but the procedures need to be carried out cautiously", said the entity's General Director, Luiz Eduardo Barata.
The Belo Monte transmission system was inaugurated in December 2017 and was submitted to tests at its maximum capacity of 4 thousand megawatts (MW) - at the time of the failure it was at 3.7 thousand MW.
The circuit breaker failure took the complex offline from the Nationally Interconnected System (SIN), which is the country's set of electrical energy transmission networks. As a protection procedure, the North, Northeast, and Southeast/Central-West networks were isolated from each other.
The Belo Monte transmission system is operated by the Chinese company State Grid. In a written communication, the company stated that a preliminary analysis revealed that the problem was provoked by the improper functioning of the circuit breaker's protection layer. According to the firm, the system was re-initialized at 4:11 PM.
Copyright Folha de S.Paulo. All rights reserved. All materials contained in this page may not be reproduced in any media, whether electronic or printed, without the prior written permission of Folhapress.