First section of Mumbai-Ahmedabad bullet train project to get powered up on November 20
You don’t have any Active Subscription.
Account subscription benefits alongside Premium Stories, Editorials, Opinions and more. Unlock these with Subscription
An aerial view of a traction substation under construction along the Mumbai-Ahmedabad bullet train corridor, a network of 14 traction substations is being developed across the 508-km corridor to support the power supply system for the high-speed rail project. Photo Credit: X/@RailMinIndia via PTI
The Mumbai-Ahmedabad bullet train project’s first section, between Surat and Bilimora, will be energised on November 20, 2026, officials of the National High-Speed Rail Corporation (NHSRCL) said on Wednesday (November 18, 2026).
“Energising the Overhead Equipment (OHE) system of the 50-km-long section between Surat and Bilimora refers to switching on the live electrical current through the Up and Down lines on the elevated corridor,” officials said.
“The Mumbai-Ahmedabad bullet train corridor is being equipped with an advanced 2×25 kV overhead traction system. The electrification network for the project comprises 14 traction substations (TSS), located along the 508-km corridor, which will receive electrical power from the grid and supply it to the overhead traction system," an official said.
“With the energisation of the overhead electrical system, the OHE wires on the specified section will remain live at all times from the date of energisation,” the NHSRCL said in an official statement.
“Members of the public, particularly residents, commuters, construction workers and other persons in the vicinity of the alignment, are strictly advised not to approach, touch or undertake any unauthorised work near the overhead electrical installations,” the statement said.
Several major components of the high-speed electrification system are now being manufactured in India. “These include all major transformers, cross arms mounted on OHE masts, as well as the ground wire, protection wire and feeder wire, which form the top electrical network of the overhead system. In addition, a large number of components related to the traction power supply system, other equipment of the distribution power system and electro-mechanical (E&M) works are also being produced domestically," an official said.
Railway officials said that India and Japan have agreed to start operations with an Indian high-speed train, which is slated to run at an operational speed of 280 kmph. The train is currently being developed indigenously by BEML Limited and Integral Coach Factory. “We will start off by using the indigenous train because India wants to make the Surat-Bilimora section in Gujarat operational by August 2027, and the Japanese E10 trains will only arrive in 2030,” an official said.
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.