Nagpur-Warangal highway will be completed by December 2027: Komatireddy
You don’t have any Active Subscription.
Account subscription benefits alongside Premium Stories, Editorials, Opinions and more. Unlock these with Subscription
The Nagpur–Mancherial–Warangal–Khammam–Vijayawada Greenfield Highway is expected to be completed by December 31, 2027, Roads and Buildings Minister Komatireddy Venkat Reddy informed the Telangana Legislative Council on Saturday.
Replying to questions raised by MLCs Pochampally Srinivas Reddy and professor Kodandaram, the Minister said the State government would take steps to ensure an exit on the highway close to Parkal, for the convenience of local residents. He said instructions would be issued to National Highways Authority of India (NHAI) officials in this regard immediately.
Mr. Venkat Reddy said the 310-km highway was a crucial connectivity project, with nearly 280 km falling within Telangana. It would connect several districts and provide an important link for people travelling from Telangana towards Nagpur and Vijayawada.
He said the Mancherial–Warangal section had been divided into packages and tenders awarded. The Letters of Award were issued on March 31, 2023, followed by agreements on May 23. The project was initially scheduled for completion within 730 days, but land acquisition issues, court cases and other factors delayed the works.
“Almost all land acquisition issues have been resolved. Only minor issues involving small stretches of land remain and these too will be settled shortly,” he said.
In view of the delay, the contractor had been granted an extension of time and the revised target for completion was fixed as December 31, 2027, the Minister said.
Referring to Prof. Kodandaram’s concerns over land acquisition, Mr. Venkat Reddy said compensation would be paid in accordance with market rates.
He said land handover was pending only at one or two locations, involving stretches of about 1 to 1.30 km at one place and 5.7 km in another package. The State government would coordinate with NHAI to resolve these issues at the earliest.
The Minister said the State government was responsible for land acquisition, while the construction work was being executed entirely under the NHAI.
He also referred to a review of the project by Union Minister for Road Transport and Highways Nitin Gadkari on May 26.
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.